‘AMORAS’ – Antwerp
Mechanical Dewatering, Recycling and Application of Silt
– operational since October 2011
25 January 2012
With the AMORAS project, there is a
permanent and sustainable solution for the treatment and
storage of maintenance dredging material in the Port of
Antwerp. This occurs by means of a unique silt treatment
system. It consists of a treatment installation for
dewatering dredged spoil and purifying process water.
The filter cakes left behind, which are at least 60%
dry, are stored or reused as environmentally friendly
material. The dewatering installation can process
approximately 500,000 tonnes of dry material (after
dewatering). The construction of the dewatering
installation was completed at the end of September 2011.
The complete system has been operational since October
1st 2011.
Sufficient draught for shipping traffic
is essential in order to safeguard the future of the
Port of Antwerp. To guarantee this draught, a large
volume of maintenance dredging material must be dredged
annually. As of now, however, a spatial saturation point
has been reached for applying former storage techniques,
such as dumping in quays on land and in overdepths (underwater
cells) in a dry dock complex. Furthermore, these
techniques have become unacceptable from a social and
environmental engineering standpoint. Therefore, the
Government of Flanders decided 5 years ago to address
the treatment and storage of dredged spoil in a new and
sustainable manner with the construction of a mechanical
silt dewatering installation in the Antwerp port area.
The project received the name AMORAS which is an acronym
for Antwerpse Mechanische Ontwatering, Recyclage en
Applicatie van Slib (Antwerp Mechanical Dewatering,
Recycling and Application of Silt). The project ensures
in a sustainable fashion the annual treatment and
storage of approximately 500,000 tonnes of dry material,
namely dredged spoil dewatered by a minimum of 60%, in
the Port of Antwerp.
The project consists of two phases. The
first phase, completed at the end of September, entails
detail engineering and the construction of the
dewatering installation. The second phase, which started
on 1 October, concerns the operation of the installation
over a period of 15 years.
The silt treatment system contains five
important zones which can be found on the location map.

Location map AMORAS project
1. Underwater cell zone:
Maintenance dredging material from the port docks is
stored temporarily by the Antwerp Port dredging company
in a newly built local underwater cell in Canal Dock B1.
It has a capacity of 300,000 m3. An electronically
driven dredging unit pumps the spoil from the underwater
cell to the shore where the treatment process commences.
More heavily contaminated spoil is not stored
temporarily but is directly suctioned from the
ladderwell containers and deposited ashore.
2. Sand separation zone: The
material pumped ashore has all course elements removed
by means of a sieve. Depending on the environmental
quality of the dredging spoil and/or the sand content,
the spoil is desanded in a sand separation installation
on the quay near the underwater cell. Hydroclones handle
the sand separation and are adjusted to a separation
point of 63 microns, the granulometric limit between
sludge and sand fraction. Separation occurs based on the
difference in density of the two fractions. The
separated course elements and sand are then transported
outside the sand separation plant via separate conveyor
belts.
3. Discharge pipeline zone: Then
the spoil, either desanded or not, is pumped over a
distance of 4 km through a discharge pipeline (2 pipes)
with a maximum throughput of 1,500 m³ per hour to the
treatment site at the ‘Bietenveld’. This is done using
low power in order to minimise energy consumption.
4. Dewatering installation zone:
At the approximately 15 ha ‘Bietenveld’ site, the spoil
is buffered into four thickening basins, each with a
capacity of 120,000 m³. Together they form a circular
basin with a diameter of 350 m. The thickening basins
ensure that the dilution water (transport water)
required for sieving, desanding and pumping the dredging
spoil is separated again after a week of sedimentation.
Three thickening basins receive the less contaminated
spoil. More contaminated spoil is deposited in a fourth
basin.
An innovative dredging system with a rotating gantry
spanning the circular consolidation ponds allows fully
automated steering of the process. The dredging gantry,
measuring 175 m, is equipped with two mobile dredge
pumps that can move along the entire span and can
operate independently of one another, which is conducive
to precision work. This makes it possible to feed the
filter press with a nearly homogeneous mixture.
In the dewatering hall the consolidated dredged
spoil is conditioned in a centrally located buffer to
which all the presses are connected. Twelve membrane
chamber filter presses dewater the spoil over five
successive working days of 24 hours (3 shifts per day)
by pressing the water through a filter cloth (in 2
phases). Cakes with a dry material content of at least
60% are left behind in the ‘chambers’. These drop onto a
conveyor belt below and are transported in this way to
the storage site. Each press (approximately 25m long, 5m
wide and 5m high), with 193 vertical chambers, can
produce approximately 30 tonnes of cakes per cycle of
approximately 1.5 hours.
The filtering water from the presses is collected
together with other waste water streams in the buffer
basin for waste water. From there it is pumped to the
biological water purification installation with a
capacity of 250 m³ per hour. The first phase in the
purification process consists of physico-chemical
pre-purification to remove fine suspended particles. In
the second phase, organic materials and nitrogen are
removed by means of biological purification. After
purification, the filtered water together with the
transport water is discharged back into Canal Dock B1
through a third pipeline.
5. Storage site zone: The filter
cakes produced are stored under controlled conditions at
the approximately 30 ha ‘Zandwinningsput’ (sand
extraction pit) site located next to the ‘Bietenveld’
site and between Hooge Maey, Indaver and the A12
motorway. The filter cakes can be stacked to a height of
50m above an already existing layer of moderately
consolidate silt already stored earlier in this sand
extraction pit. Using phased and controlled storage, the
aim is for an operation period of at least thirty years.
As soon as possibilities for reuse of the filter cakes
arise in future, this duration can be extended even
further.
In the middle of 2008, the significant
AMORAS contract was awarded to the temporary trade
association SeReAnt, a combination of Flemish dredging
company Jan De Nul and Dredging International (DEME),
supported by their respective environmental contractors
Envisan and DEC. The awarded amount of approximately EUR
480 million incl. VAT includes construction costs,
operation costs and the cost of financing. Construction
represents an investment of EUR 118 million. To this
end, the Government of Flanders has freed up EUR 46
million in current resources in the construction period
(2008-2011). The balance of EUR 72 million is financed
by the contractor and will be repaid during the
operation phase. Every operation year demands an
investment of EUR 29 million, 22 million of which for
the actual operation and 7 million for repayment of
financing.
Construction was completed on 30
September 2011. This is 6 months later than originally
planned due to 2 exceptionally harsh winters (3 months
arrears) and necessary changes to the underwater cell
and the pipeline which emerged during the course of
construction. Actual operation of the treatment
installation started on 1 October 2011 and concludes,
after 15 years of operation, at the end of September
2026.
“With a fine feat of environmental
technology, AMORAS provides an answer to the flanking
policy I envision upon achievement of important
investments and works. With this initiative we have made
the switch to new, future-oriented treatment techniques
reliable over a longer term. AMORAS guarantees efficient
use of space and a good environmental score: care was
taken to ensure minimal energy consumption; the purified
waste water is of a very high quality; and maximum reuse
of the water has been taken into account. Together with
the Antwerp Port Authority, with private companies
Wienerberger, Argex and De Rycke Cement and with the
research institutions Flemish Institute for
Technological Research, Belgian Road Research Centre and
the Belgian Building Research Institute, and in the
framework of the research project VAMORAS, in the coming
months the Government of Flanders will investigate the
extent to which the waste material (filter cakes) can be
reused. This is sustainability at its best.” according
to Hilde Crevits.
Press information:
Cybelle-Royce Buyck
Spokeswoman of Flemish Minister Hilde Crevits
Mobile: 0486 14 12 72
Persdienst.crevits@vlaanderen.be
www.hildecrevits.be
back
|